ANALISIS KOORDINASI DAN SETTING OVER CURRENT RELAY (OCR) PADA PEMAKAIAN DAYA SENDIRI PLTU SMS ENERGY MENGGUNAKAN SOFTWARE ETAP 12.6.0

  • Nursalim Nursalim(1*)
    Universitas Nusa Cendana https://orcid.org/0000-0002-9291-9609
  • Agusthinus S. Sampeallo(2)
    Universitas Nusa Cendana
  • Ahieser P.L Willi(3)
  • (*) Corresponding Author
Keywords: Over Current Relay, Koordinasi OCR, Grading time, Settingan OCR, ETAP 12.6.0, OCR Coordination

Abstract

ABSTRACT

The research aims to determine the size of the OCR Motor Pump, Grading Time OCR Motor Pump, coordination Motor Pump OCR and auxiliary OCR on PLTU SMS Energy in the Bolok industrial area.  Research started by collecting electricity data PLTU SMS Energy in the form of secondary data. These data are used to create single line diagrams, simulations and analysis using ETAP 12.6.0. The results of the research get an  OCR Setting with the following short-circuiting value parameters.  Setting relay Bus 1 FCP with Ip = 3 A and TMS = 0.1 s, setting relay Auxiliary bus I with IP = 2 A and TMS = 0.21 s, setting relay bus OutGoing 1 with IP = 0.6666 A and TMS = 0.30 s and setting relay bus G1 with IP = 1 A and TMS = 0.45 S. TMS OCR on Pump motor is plotted faster due to the most downstream OCR location with smaller short-circuited tension. From the coordinating curve of Grading Time obtained that has been in accordance with IEEE Standard 242-namely  0.2 – 0.4 seconds.

 Keywords: Over Current Relay, OCR Coordination, Grading time, OCR setting, ETAP 12.6.0

 

ABSTRAK

Penelitian ini bertujuan untuk mengetahui besaran settingan OCR Motor Pump, Grading Time OCR Motor Pump, koordinasi OCR Motor Pump dan OCR auxiliary pada PLTU SMS Energi di kawasan industri Bolok.  Penelitian diawali dengan mengumpulkan data kelistrikan PLTU SMS Energy berupa data sekunder. Data-data tersebut digunakan  untuk membuat single line diagram, simulasi dan analisis menggunakan  ETAP 12.6.0. Hasil Penelitian mendapatkan Settingan OCR dengan parameter nilai arus hubung singkat sebagai berikut. Setting Rele Bus 1 FCP dengan Ip = 3 A dan TMS = 0,1 s,  Setting Rele Bus Auxiliary I dengan Ip = 2 A dan TMS = 0,21 s, Setting Rele Bus OutGoing 1 dengan Ip = 0,6666 A dan TMS = 0,30 s dan Setting Rele Bus G1 dengan Ip = 1 A dan TMS = 0,45 s. TMS OCR pada motor Pump disetting lebih cepat karena letak OCR paling hilir dengan ganguan hubung singkat lebih kecil. Dari koordinasi kurva didapatkan Grading Time yang sudah sesuai dengan standar IEEE 242-yakni 0.2 – 0.4 detik.

 Kata Kunci: Over Current Relay, Koordinasi OCR, Grading time, Settingan OCR, ETAP 12.6.0

Downloads

Download data is not yet available.

Author Biographies

Nursalim Nursalim, Universitas Nusa Cendana

Program Studi Teknik Elektro, Fakultas Sains dan Teknik Universitas Nusa Cendana

Agusthinus S. Sampeallo, Universitas Nusa Cendana


Program Studi Teknik Elektro, Fakultas Sains dan Teknik Universitas Nusa Cendana

References

Kiswondo, Panduan Pemeliharaan Rele Proteksi, Merak: PT. Indonesia Power, 2014.

M. Afik, Interviewee, Pengambilan Data Penelitian Tugas akhir. [Interview]. 14 November 2018.

B. and A. Priyanto, "Analisa & Optimalisasi Koordinasi Rellay Proteksi Sistem 6 kV Auxilliary PLTU Banten 3 Lontar," Sinergi Vol. 19, No. 3, pp. 187 - 194, 2015.

D. F. Efisiyanto, J. and K. , "Evaluasi Drop Voltage dan Setting Relay OCR, GFR dan Recloser Pada Penyulang Kalisari 1, 6 dan 11 Menggunakan ETAP 7.5.0," Transient Vol. 4, No. 3, pp. 508-516, 2015.

J. M. Gers and E. Holmes, Protection of Electricity Distribution Networks 2nd Edition, London: The Institution of Engineering and Technology, 2004.

A. W. Hidayat, H. Gusmedi, L. Hakim and D. Despa, "Analisa Setting Rele Arus Lebih dan Rele Gangguan Tanah pada Penyulang Topan Gardu Induk Teluk Betung," Electrician Vol. 7, No. 3, pp. 108-115, 2013.

A. Grid, Network Protection and Automation Guide 2011 Protective Relays, Measurement & Control, Paris: Alstom Grid, 2011.

J. J. Grainger and W. D. J. Stevenson, Power System Analysis, New York: McGraw-Hill Book Company, 1994.

H. Samaulah, Dasar - Dasar Sistem Proteksi Tenaga Listrik, Palembang: Universitas Sriwijaya, 2004.

W. Sarimun, Proteksi Sistem Distribusi Tenaga Listrik, Depok: Geramond, 2012.

D. Marsudi, Operasi Sistem Tenaga Listrik, Jakarta Selatan: Balai Penerbitan & Humas ISTN, 1990.

A. F. Panjaitan, Hermawan and Y. , "Evaluasi Setting Proteksi Arus Lebih Di Jene Station PT. Medco E&P Indonesia Dengan Menggunakan ETAP 12.6.0," TRANSIENT, VOL. 5, NO. 3, pp. 365-372, 2016.

Y. Triyono, O. Penangsang and S. Anam, "Analisis Studi Rele Pengaman (Over Current Relay Dan Ground Fault Relay) pada Pemakaian Distribusi Daya Sendiri dari PLTU Rembang," Jurnal Teknik Pomits Vol. 2, No. 2, pp. 159-164, 2013.

K. "Koordinasi Rele Arus Lebih Di Gardu Induk Bukit Siguntang Dengan Simulai ETAP 6.0.0," Jurnal Media Teknik, Vol. 8, No. 3, pp. 94-106, 2011.

L. Erwansyah, R. S. Wibowo and M. Pujiantara, "Proteksi Ground Fault Untuk Sistem 11 kV dengan Multiple Bus yang Terhubung Beberapa Generator, Bus Ties, dan PLN, dengan Sistem Grounding yang Berbeda-Beda," Jurnal Teknik Pomits Vol. 1, No. 1, pp. 1-6, 2012.

A. R. Permana, "Studi Koordinasi Rele Proteksi Pada Sistem Kelistrikan PT. BOC Gases Gresik Jawa Timur," Jurnal Teknik Pomits Vol. 2, No. 2, pp. 1-6, 2006.

T. Gonen, Electric Power Distribution System Engineering, New York: McGraw Hill, 1985.

Sujito, "Koordinasi Proteksi Arus Lebih Pada Jaringan Distribusi Menggunakan Software Edsa 2005," Tekno, pp. 27-36, 2013.

PT PLN (Persero), Buku Pedoman Pemeliharaan Proteksi dan Kontrol Transformator, Jakarta Selatan: PT PLN (Persero), 2014.

Yusmartato and Yusniati, "Analisa Relai Arus Lebih Dan Relai Gangguan Tanah Pada Penyulang LM5 Di Gardu Induk Lamhotma," Journal of Electrical Technology, pp. 27-37, 2016.

PlumX Metrics

Published
2019-10-30
How to Cite
[1]
N. Nursalim, A. Sampeallo, and A. Willi, “ANALISIS KOORDINASI DAN SETTING OVER CURRENT RELAY (OCR) PADA PEMAKAIAN DAYA SENDIRI PLTU SMS ENERGY MENGGUNAKAN SOFTWARE ETAP 12.6.0”, JME, vol. 8, no. 2, pp. 97 - 106, Oct. 2019.
Section
Articles